Library Building Lighting Replacement, USC Upstate

The USC Upstate Library had previously been up-fitted with new fixtures in certain areas by in-house staff. The purpose of this project was to allow for the remainder of the first floor to be completed in a timely manner. Demolition began the day after graduation, including the lighting, wiring and acoustical ceiling system in the first floor. Once the ceiling, lights and HVAC diffusers were down, and the conduit and wiring was secured in the ceiling, new installation began immediately. 

The new ceiling tile system was to be upgraded not only for aesthetics, but also to bring it up to current IBC seismic codes. The lights and HVAC had to be installed and secured accordingly as well. Over 200 lights were demolished and replaced during this project. The new lights in the classrooms and offices were installed with optical sensors to allow for energy conservation when not in-use. 

  • Location: Spartanburg, SC
  • Date: May- July '13
  • Owner: USC Upstate
  • Engineer: Burdette Engineering
  • Remove and replace ceiling system
  • 1st floor Campus Library
  • Remove and replace 200 fluorescent light fixtures
  • IMAG0967
  • IMAG0968
  • IMAG0969
  • IMAG0970
  • IMAG0971
  • IMAG1070
  • IMAG1072
  • IMAG1141
  • IMAG1142
  • IMAG1143
  • IMAG1144
  • IMAG1145

Educational Projects

  • Campus Life Building HVAC Replacement, USC UpstateCampus Life Building HVAC Replacement, USC Upstate
  • Library Building Lighting Replacement, USC UpstateLibrary Building Lighting Replacement, USC Upstate
  • Gov. School- Lipscomb Art GalleryGov. School- Lipscomb Art Gallery
  • Library Lighting Replacement: Phase II USC UpstateLibrary Lighting Replacement: Phase II USC Upstate
  • Clemson University- Byrnes Hall Interior RenovationsClemson University- Byrnes Hall Interior Renovations

Other Projects

the Highlands Group of the Carolinas has a variety of in house capabilities.

Industrial Projects
Industrial Projects
Commercial Projects
Commercial Projects
Residential Projects
Residential Projects
Cable pulling 101, make sure you have plenty of cable lubricant! #tuggAlmost ready for Final Inspection! #barndoor #renovations #designbuildNew Cree LED fixtures installed...after finally finding the correct ciGrading and asphalt for the new driveway and handicap parking area. HuDO NOT put glue on the threads! #servicecall #hvac #whyismyacleaking #Monday's be like! #monday #servicecall #werenotonwheniparked #AssociatService call for an exhaust fan 
Motor. Shaft alignment, belt tension,60'x16' shed for a customer. This one was rebuilt after a winter stormWhen concrete is involved, sunshine CANNOT be taken for granted! #conc

Error Message

×